We were thrilled with the progress last time we visited the house, but were perhaps a little disappointed that we couldn’t get in and show the folks around. We took the other side of the family through yesterday, and whilst on the surface not a lot appears to have happened, on closer inspection they’ve done quite a bit in the last week.
For starters, the roof looks to be now pretty close to finished. All the points are done, and it looks like they’ve been pulling up bits of tiles to finish off the gutters as well. The walls are now all full bricked all the way around and whilst we’re still waiting for the sills to be done, everything else looks like it is pretty much done outside. It’s not until I look back at the photos that I realise that they’ve also plastered up under the eaves, and look to be prepping the garage lintel for rendering as well! So hopefullythat will happen this week too.
Inside, all the cornices are up, and they’re in the process of doing the skirting boards. The plaster is all filled, patched, puttied and ready to be painted.
The alfresco is now pretty much done, with a roof and the external roof supports removed..also looking like its being prepped for render and paint.
The floors are all hideously dirty… but we assume they’ll clean those before they do the floors
All of our internal doors have arrived, and are ready for installation!
The windows have had the joinery around the outside of the frames…and again, everything looks like it’s getting ready to paint.
So whilst on the surface it looks like not much has happened, after a good look around they’ve been really quite busy! We still aren’t officially at lockup, but they’re already quite a way into doing the fixing! Go Urbanedge!